In a significant development, the Union Ministry of Environment, Forests and Climate Change (MOEF&CC) has denied Andhra Pradesh’s (AP) request for environmental clearance terms for the controversial Godavari-Banakacharla link project.

Salamah Advt

Hyderabad: In a significant development, the Union Ministry of Environment, Forests and Climate Change (MOEF&CC) has denied Andhra Pradesh’s (AP) request for environmental clearance terms for the controversial Godavari-Banakacharla link project. This move is being hailed as a major victory for Telangana, which has consistently opposed the project.

Environmental Clearance Denied Due to Inter-State Water Disputes

The Expert Appraisal Committee (EAC) of the MOEF&CC, during its meeting on June 17, noted several unresolved issues related to Godavari water sharing between AP and Telangana. The committee stated that the project might violate the 1980 Godavari Water Disputes Tribunal (GWDT) award.

The committee concluded that AP must consult the Central Water Commission (CWC) to assess the availability of floodwaters before even submitting a proposal for Terms of Reference (ToR), which is a prerequisite for an Environmental Impact Assessment (EIA).

Telangana’s Concerns Echoed by the Centre

The Telangana government, led by Chief Minister A. Revanth Reddy, had raised objections to the project multiple times, including in a recent meeting with Union Jal Shakti Minister C.R. Patil on June 19. Telangana argued that the Godavari-Banakacharla link project would harm the state’s water interests and was being pursued by AP without proper inter-state agreements.

Project Faces Multiple Environmental Hurdles

The Godavari-Banakacharla project, as proposed by Andhra Pradesh, has several critical environmental concerns:

These factors further strengthen the case for withholding environmental clearance until a detailed review and inter-state consultation is conducted.

What’s Next for the AP Government?

With the rejection of ToR, the AP government cannot proceed with its planned EIA study, effectively stalling the project. The pre-feasibility report submitted earlier is not sufficient to move forward, and CWC clearance is now mandatory.

The Centre’s decision aligns with Telangana’s stance and emphasizes the need for inter-state coordination, environmental safeguards, and adherence to legal water-sharing agreements before launching large-scale infrastructure projects.