Blasting Ahead! Major Shift in SLBC Tunnel Strategy Recommended

The Technical Committee appointed to review the Srisailam Left Bank Canal (SLBC) Tunnel project has recommended that the government abandon the Tunnel Boring Machine (TBM) method at the inlet side and instead proceed with the Drilling and Blasting (D&B) technique.

Hyderabad: The Technical Committee appointed to review the Srisailam Left Bank Canal (SLBC) Tunnel project has recommended that the government abandon the Tunnel Boring Machine (TBM) method at the inlet side and instead proceed with the Drilling and Blasting (D&B) technique.

The expert panel concluded that tunneling with TBM is unfeasible due to geological challenges and that only drilling and blasting can ensure safe and effective excavation.

Central Environmental Clearance Must Be Followed

The committee also emphasized that any excavation activities should strictly adhere to the guidelines and clearances issued by the Union Ministry of Environment, Forest and Climate Change. It stressed the importance of legal compliance during the execution of tunneling operations.

To enhance safety and precision in excavation:

Timeline and Technical Deadlines Issued

The expert panel has set a detailed timeline for executing the recommendations:

Cost Estimates and Revised Work Plan to Be Submitted

The committee further instructed the authorities to:

The SLBC project plays a vital role in channeling water from the Srisailam reservoir to drought-prone regions of Andhra Pradesh and Telangana. With these latest expert recommendations, the project may see faster progress and improved worker safety, especially in challenging geological conditions.