Tunnel Tragedy in Telangana: Fault Zone Ignored, Lives Lost

The tragic SLBC tunnel collapse, which claimed the lives of eight workers, has intensified scrutiny on Jaiprakash Associates for alleged negligence in addressing long-flagged geological risks.

Hyderabad: The tragic SLBC tunnel collapse, which claimed the lives of eight workers, has intensified scrutiny on Jaiprakash Associates for alleged negligence in addressing long-flagged geological risks. As rescue operations to locate the six remaining workers have been called off, government officials and experts are raising serious concerns about safety, accountability, and the lack of due diligence in the project’s execution.

Jaiprakash Associates Ignored Fault Zone Risks, Reports Say

A senior official from the Irrigation Department of Telangana confirmed that the collapse site—13.9 km inside the Srisailam Left Bank Canal (SLBC) tunnel—was located within a known fault zone. The area was explicitly identified as geologically unstable in multiple Tunnel Seismic Prediction (TSP) reports, including a critical 2020 study by Amberg Tech AG.

“The incident could have been avoided. The location was flagged for water-bearing zones and fractured rock mass years ago,” the official stated.

The TSP-303 Plus system used in the 2020 study pinpointed dangers like reduced rock stiffness, jointed formations, and high water seepage potential—all of which were ignored before resuming work in early 2025.

SLBC Collapse Timeline: Known Danger Ignored

A 2020 research paper co-authored by a former GSI official and a Jaiprakash Associates geologist admitted that tunneling began without full subsurface exploration, relying instead on remote sensing due to environmental restrictions in the Amrabad Tiger Reserve.

The Telangana government has held Jaiprakash Associates contractually liable for the tragedy and its financial fallout. Questions remain about whether the agency shared seismic findings with the government or incorporated them into its construction risk strategy.

“There was no review of the 2020 report before work resumed. That alone reflects a glaring failure in oversight,” the official added.

Call for Accountability and Tunnel Safety Reform

The SLBC tunnel collapse has reignited calls for:

The tragedy highlights a dangerous pattern in infrastructure project management, where cost and timeline pressures override geological realities, placing workers’ lives at risk.